Lake Street will open this weekend from 6.00pm Friday 29 September to 7.00am Monday 2 October.
Lake Street status this weekend: OPEN, 6.00pm on Friday 29 September, to 7.00am on Monday 2 October.
Unfortunately the weather last week has led to some work delays on Man Street, however overall the team and work has been progressing well.
With our first layer of asphalt down this week, we are hoping to get our final layer (with works in between) complete in the next few weeks. If all goes to plan we will be targeting for an opening date of Friday 20 October for Lake Street. We will keep you updated weekly on progress and the estimated completion date.
Please see the table below outlining what we completed this week, and what we have coming up next week.
|
Completed this week |
Paved two layers of structural asphalt Started exposing and setting manhole lids ahead of the final layer of asphalt Installed kerb and channel at the Man/Hay Street intersection |
|
Next week (29 Sept – 6 Oct) |
Continue exposing and setting manhole lids ahead of the final layer of asphalt Footpath construction on Man Street adjacent to the Lake Street intersection Pavement construction at the Lake/Man Street intersection tie in |
As always, our top priority is the safety of all residents and commuters, so we kindly ask for you to please follow the traffic and pedestrian signs and take extra care at all times.