Ballantyne Road Upgrade

A project is underway to vastly improve safety on Ballantyne Road, Wānaka.

About the project Road closure Other things to expect Get in touch

About the project

Jointly funded by Council and Waka Kotahi NZ Transport Agency, the upgrade   will start on 3 December and address a number of safety issues such as inconsistent surfacing, limited driver sight lines, a lack of road markings and narrow roadways.     

Fulton Hogan has been appointed to complete the project which is expected to take approximately 6 months to complete.  

Key improvements include

  • The sealing of 4km of unsealed road and clear zone on both sides, significantly reducing the risk of crashes in the area.

  • A low speed environment by design

  • One metre wide sealed shoulders to allow safer opportunities for walking and cycling

  • Improved drainage

  • The relocation of 40 power poles in conjunction with Aurora

We will also be working with Chorus, Spark and Vodafone to facilitate planned future network upgrades between Wanaka and Luggate and avoid works on the upgraded road at a later date

Road closure

For the project to be completed safely, Ballantyne Road will be closed to through traffic starting on Thursday 3 December for approximately 6 months. 

Our contractors will ensure access is maintained for residents living along Ballantyne Road (including those of Boundary and Morris Road) and essential services over this period.

For all others a detour will be in place via Riverbank Road & SH6. 

Please allow  extra time for your journey if you're driving out this way and follow all signage in place.   

Other things to expect

There are some other things to be aware of while the work is underway: 

Fence Relocation

Where existing fencing is within road reserve, the fenceline will be reinstated on the legal boundary. Council will cover all costs associated with the relocation.  Where the age and condition makes relocating the fence unviable, Council will replace the fence like for like. 

If you're affected by this, Fulton Hogan will be in touch with you soon to co-ordinate the work.

Accessways

Council will seal existing accessways to the road boundary.

Tree removals in road reserve

A number of trees will need to be removed from within the road reserve to accommodate the improvements. 

 All care will be taken to ensure trees that are to be retained are not damaged by construction activity.

In lieu of removing trees along Ballantyne Road, we’ll be working with Te Kākano Aotearoa Trust and the local community to support the planting of the wetland area adjacent to Atherton Place along the track between Bremner Bay and Penrith Beach

Tree pruning

To ensure the route is freely accessible on completion, a number of trees along the route are required to be pruned to give a clearance from the ground of 5m.

Dust

Water trucks will be used to suppress dust during the construction period.

Get in touch

If you have any questions or concerns you can either contact QLDC or Fulton Hogan:

QLDC Project Manager
Alison Howie
03 441 0499      
alison.howie@qldc.govt.nz    

Fulton Hogan Ltd
Andrew Dennison, Construction Manager
0272753767

Thanks  for your patience while we carry out this essential upgrade work. 

Stay up-to-date

Sign up to our newsletter Scuttlebutt and stay up-to-date with the latest news, events & information in the Queenstown Lakes District.