Thursday, 12 November 2026
Frankton Track to reopen ahead of schedule
The track has been closed since January while crews installed a new wastewater pipeline.
Queenstown Lakes District Council (QLDC) is pleased to announce that the Frankton Track will reopen ahead of schedule, allowing residents and visitors to once again enjoy access to the popular trail.
The track has been closed since January while crews installed a new wastewater pipeline. It will reopen ahead of the Queenstown Marathon on Saturday 14 November and remain open thereafter, around one month earlier than originally anticipated.
QLDC Property and Infrastructure General Manager Tony Avery said the early reopening was the result of a significant effort by everyone involved.
Over the past month, project teams have worked seven days a week to complete critical construction activities and restore public access to the track earlier than planned.
“We know how important the Frankton Track is to residents and visitors who use it every day for walking, running and cycling,” Mr Avery said.
“We want to thank residents, businesses and track users for their patience and support throughout construction. We know people will be pleased to have access restored and to see the track reopen.”
Previous communications indicated the track would need to close again until Christmas. With the project now ahead of schedule, that extended closure is no longer required.
While the full trail will remain open after the marathon weekend, sections of the track will continue to be diverted onto scaffolding until mid-December. This will allow crews to install the final section of pipeline and complete sealing works on the trail adjacent to the scaffolding.
The project, which began in January and is being delivered by QLDC and McConnell Dowell, has involved extensive construction along the Frankton Track corridor to install a new wastewater pipeline and associated infrastructure.
Since works began, crews have installed 3.2 kilometres of pipeline along the Frankton Track and 900 metres of pipeline across Frankton Beach, including through the Frankton Beach reserve and track corridor. To make way for the pipeline, crews removed approximately 2,800 cubic metres of rock along the Frankton Track. The project has also involved installing 10 kilometres of utility ducts along the corridor and approximately 50 stormwater culverts to improve drainage and resilience.
Some final reinstatement works, including topsoiling and planting, will continue over the coming months. Short temporary closures may occasionally be required to safely complete minor works. Any future closures are expected to last no more than one or two days. Advance notice will be provided, and every effort will be made to minimise disruption and keep the track open wherever possible.
The new pipeline will help support future growth and improve the resilience of the district's wastewater network.
ENDS | KUA MUTU.
Media contact: 03 441 1802
FURTHER INFORMATION | Kā pāroko tāpiri
Image: Frankton Track will reopen for Queenstown Marathon and stay open.